Onshore Oil & Gas
Pipelines, Fractionation and Liquefaction, Permico Midstream Partners
The project brings Y-Grade feedstock 870 km from West Texas to a fractionation plant through a 500mm pipeline. The gas pipeline include 5 pumping / pigging stations.
The fractionation plant provides purity products. HP Compression to liquids are sent to sphere storage.
The liquids pipeline would carry HP purity products 600km through a 400mm pipeline to the East Texas Gas Hub. Two pumping/pigging stations are included.
A liquefaction plant (gas chillers and refrigerant compressors) provide liquefied product to LP storage tanks.
A LPG loading wharf with 2 sets of 5 loading arms are available for purity offloading to LNG carriers for international export.


Project: Ethane Cracker and Derivatives Plant
Location: Louisiana, USA
Builder: Fluor / Technip
End user: Sasol
Status: Operational, 2019
Role: Mechanical Completions and Commissioning Support